Elenga-Rangpur Four-Lane Conversion: More time, more money required
The
government in September 2016 approved a project to turn a 190km two-lane road
from Elenga to Rangpur into a four-lane highway with the view to boosting
connectivity between the capital and the northern region.
The mega project, implemented by the
Roads and Highways Department with loans mostly from the Asian Development
Bank, was supposed to be implemented within June 2021 at a cost of Tk 11,899
crore.However, the project authority could not start the physical works until
2020 and added some new elements, resulting in a major revision of the project.
Now, the revised cost of the project
is Tk 19,016 crore and the deadline is December this year.The project saw 75
percent progress so far as the authority could not even start construction of
two major flyovers in Gaibandha due to long delays in land acquisition.
So, the project authority sought two
more years, including a one-year defect liability period, and Tk 40 crore to
complete the job.
The revision proposal is now pending
with the road transport and highways division and will be sent to the Planning
Commission soon, according to officials informed with the proceedings.If the
proposal is approved, the project cost will rise to Tk 19,056 crore, which
would be Tk 7,157 crore (60 percent) higher than the original estimate. The new
deadline will be December 2026, which is five-and-a-half years more than the original
timeframe.
In this situation, the Road Transport
and Highways Minister Obaidul Quader yesterday opened one railway overpass,
seven road overpasses and two bridges built under the project.
"These are opened to traffic as
the prime minister's Eid gift to homebound people," Quader said after
opening the structures virtually.Under the project titled South Asia
Subregional Economic Cooperation (SASEC) Road Connectivity Project-2, the 190km
road from Elenga of Tangail to Rangpur will be turned into a four-lane highway
with service lanes on both sides.
RHD has already expanded a 70km road
from Gazipur to Elenga into a four-lane highway under SASEC Road Connectivity
Project-1 and Dhaka-Gazipur highway under a different project.There are plans
to turn a 320-km two-lane road from Rangpur to Banglabandha, Rangpur to
Burimari and Rangpur to Sonahat into a four-lane highway along with service
lanes to boost regional connectivity, according to RHD officials.
So far, construction of 150 km of
pavement out of 190km has been completed along with all 180 culverts, 18 out of
the 32 bridges, 25 out of the 39 overpasses, one out of five flyovers, said
SASEC-2 project officials.However, construction works of two flyovers at
Palashbari and Gobindaganj could not be started due to delays in land
acquisition, Project Director Waliur Rahman told The Daily Star on Wednesday.
Besides, work for a major interchange
at Hatikumrul and a flyover at Elenga got delayed due to land
acquisition.However, the problem has now been solved, he added.An official of
the project said they have appointed a contractor for building Hatikumrul
interchange in January 2022 but they received land in November that year,
hampering the works.
They received land for Palashbari
flyover in January this year while from local administration last week asked
them to receive land for Gobindaganj flyover, he said wishing not to be
named.Covid outbreak and Russia-Ukraine war were other reasons behind the cost
and time overrun, he added."We hoped to complete all construction works
within 2025," Waliur Rahman said.So, they sought time up to December 2026
with one year defect liability period and additional Tk 40 crore, he added.
Comments
Post a Comment